The final phases

Over at the k35 project the first of two is progressing extremely well. Next week will bring us deep into the final phases of the build. First up is electrical final followed by trim and doors being re hung, then plumbing final. After all that we can bring in appliances and the last coat of paint. Iā€™d estimate all that to be around three weeks of work. The first side will likely be staged for sale and have a nice window covering package installed.

Tile is grouted and hardwood installed.  Nice week of progress at the k35 site.

Tile is grouted and hardwood installed. Nice week of progress at the k35 site.