Rowhouse preparation for gas and electrical meters

the rowhouse project has now progressed to the stage where we need to get serious about the service installations.  We’ve now prepared for gas meters and the six electrical bases where the utility provider will install the overhead wires and meters.  

This work generally requires a fair bit of lead time, inspections and creation of accounts.  I’ve taken care of the bulk of that and we can now call the providers to connect.  

 

IMAGE.JPG

six electrical meters are due to be installed here.  The service is overhead rather than underground from the garage.  This is a much easier way to do it, though less clean looking. 

 

IMAGE.JPG

dual masts are bolted to long smartboard planks that I’ve prepainted.  What a relief to have warm enough weather to do some outside work in relative comfort.