Drywall begins - Pace of construction comparison

With drywall underway, we are now moving into the finishing stage of the project, always a happy milestone.  The interesting comparison to make here is the time lost vs the last project from inspections to starting drywall.  Unfortunately we have now lost much of the time advantage over a previous build.  The weather, holiday season, and some permit delay cost us almost two weeks.

Previous project inspection to drywall - 5 days

Current project inspection to drywall - 22 days.  

While extremely frustrating to lose so much time (a lot of it between dec 20 and Jan 5th), the current project is still ahead of the previous project.  

Previous project footing to drywall - 104 days

Current project footing to drywall - 96 days.

So the pace of construction has now narrowed, unfortunately if we had been a little quicker and luckier the drywall would have been complete before Christmas.

Drywall going on the ceiling, a lot of work has gone into the project to date, 96 days to get here.

Drywall going on the ceiling, a lot of work has gone into the project to date, 96 days to get here.