Garage building part 3

In the overall grand scheme of garage building we are still in the early stage, but we are moving along now nicely.  The pad is largely prepped and rebar is tied. We have an engineer inspection date and a pour date. If all goes well we will immediately deliver the lumber and roof package, and the framers will be back.  Here is some work done from today

Early phase of slab prep.  note the thickened edges and the tighter rebar grid than the norm.

Early phase of slab prep.  note the thickened edges and the tighter rebar grid than the norm.

View from the apron that has yet to be finished.  This is a large four bay garage, and a lot of material goes into the slab.  I have some experienced guys doing the prep and like their workmanship thus far.

View from the apron that has yet to be finished.  This is a large four bay garage, and a lot of material goes into the slab.  I have some experienced guys doing the prep and like their workmanship thus far.