Rowhouse framing part 2

With the main floor of building 2 and 3 mostly sheated, we can get a good impression of how spacious the rowhouse units will be, and how high the main floor is off the grade at the sidewalk.  So far it is working out very well, expect some walls up very soon.  

noj7azlsSKaiJZYeEKOnLw.jpg

  With the main floor sheated, we can get out of the dirt and work on a flat surface.  Or at least the framers can, my job these days seems to be mainly writing cheques and dealing with trash.

 

IMAGE.JPG

lower levels are also progressing.