K35 - 1 month update
Lots of progress to report at the k35 semi detached project as we have just passed the one month milestone from the day we poured the footing to early this week. We finished the first full construction month with the shingles on and the basement slabs poured. The plumber is partway through the drainage network, and can now get down into the basement to do the network under the main floor. Decent weather and a good framing crew has enabled all the other associated activity. We are now going to get the garage started and move into Hvac and electrical as we approach the end of September. Overall a really good start to the project.