Framing begins
Finally some above ground work is underway at the semi detached project. We lost a week due to some extremely cold weather but our framers are now on site and capping the main subfloor.
It often seems at this stage of the project such a significant passage of time and effort has taken place that we are at the end, rather than the very beginning of a job. Many of the next series of tasks is predictable and efficient compared to the launch of a new house project where weather and heavy equipment schedules need coordinated.
We will have enough lumber supplies delivered this week to get us through the holiday season and hopefully a framed house in another four weeks.